Maintenance Work in the Library Beginning February

IMGP7883Beginning on Monday 2nd February Facilities Management will be replacing two aging chiller units in the basement of the Library building Plant Room.

These units are being replaced during the colder winter period as the cooling units are not deemed as necessary so much at this time. It is hoped the Library will be able to have a more stable temperature once these poorly performing units have been replaced.

This work is expected to be finished by Friday 17th April. It is not anticipated that this work will cause much noise or disruption to the Library in general as it will be carried out via the loading bay at the rear of the building. However the access road between the Library and the entrance to the Village Bar may be blocked at times while the contractors carry out the work.